Faulenbach da Costa, who has been planning airports since 1985 and has accompanied the BER airport project as a consultant, says that even in the 1990s it was clear that the German capital would grow and that the Schnefeld area was too close to the city and wouldn't be expandable. In 2014, it was discovered Fire-doors didnt open, miles of cables were mislaid, and a vast smoke-extraction system was ineffective. The company had previously filed an application to allow noise levels to exceed 55dB up to six times a day. that this much-needed airport will open in 2020 or maybe 2021. As construction works began, the airports opening date was set for October 2011. Some lights couldn't turn on; others couldn't turn off. By 2006, the Federal Administrative Court one of Germanys federal supreme courts approved the plan to convert Tegel into Berlin-Brandenburg International Airport, allowing the initial ground-breaking works and site preparation. Preparatory construction work began. A spokesman for the new airport, Lars Wagner, waved off questions on what could have been done to prevent the delays and cost overruns. It may be a more muted moment for those close to the airport's famous namesake, Willy Brandt. Finally, political-economic explanations see overrun as the result of strategic misrepresentation of scope or budgets. There are unfortunately Whether the German capital's new hub can open on 17 March 2013 - the latest target date after the inauguration was delayed from 3 June this year - is not yet clear. The reasons for the continued uncertainty The reason for the postponement was attributed to fire safety standards. Schnefeld was chosen not only because of its proximity to the capital, but also because both Berlin and Brandenburg could gain economic benefit from the investment. Berlin Brandenburg: The airport with half a million faults German engineers like me have felt embarrassed.. "It's gotten to the point that our friends from Southeast Asia who've invested a lot in Germany and buy our expertise are starting to think twice," he says. to a large number of systemic problems that have resulted in construction The official groundbreaking didn't happen for another decade. He is deeply committed to seeing your construction project succeed. Conception to operation has taken 30 years, with seven missed opening dates. shops, 5 km from ski slopes, free shuttles 300m. If you have A 1994 regional planning procedure had already flagged the risk, concluding that the area was unsuitable for the planned two runways and an annual passenger volume of 30 million. analysis you need to keep the trust and faith of those relying on you for a many instances of scope creep with the Brandenburg airport. citizens of Berlin, the owners of the airport shops, restaurants, retail, and Just before the opening date, inspectors reported some 120,000 defects, including fire safety issues, automatic doors that didn't open and sagging roofs. Gerkan and his team were sent packing. For example, consider a bridge with a construction budget of $100 million where the actual cost was $150 million. The cost overruns exceeded the original budget by 50%. A stick of dynamite would provide more order than trying to clean the airport up. What Happened to the Berlin Brandendburg Airport? - Project Cost Solutions It has cost taxpayers around 7 billion more than three times the originally estimated sum of 2 billion.